APRIL 2018 - SIS Compliance

Our client had recently invested $300 million in constructing a new oil storage facility. During that projects development a project risk assessment (HAZOP & LOPA) had been completed with an output that identified a requirement for 8 safety instrumented functions. During a post project audit it was determined that the applicable international standards IEC 61508 & 61511 had not been complied with and that corrective action was urgently needed.

 

Fabri Consulting Engineers completed the following work within months of receiving the clients instructions:

 

SIL Validation

  • Site survey to gather as-built information;
  • Equipment investigation;
  • Complete SIL validation calculations (8 No. SIFs); and
  • SIL validation report.

SIF Design and Management

  • Safety Requirement Specification (SRS);
  • Safety management plan;
  • Complete proof test procedures (8 No. SIFs);
  • Commissioning and verification review and recommendations;
  • Functional safety assessments for stages 1, 2 and 3;

  • Functional safety plan and audit schedule; and

  • Review of deliverables with client and subsequent requested updates.

 

The client is now undertaking the recommended actions to ensure the Terminal can be demonstrated to be safe to operate.

Douglas Burns

NOVEMBER 2017 - Quality Management Surveillance Audit

Following the successful transition to the new ISO9001:2015 Quality Management system in November 2016, Fabri have completed their first surveillance visit of the three year cycle.

 

The auditor representing the independent certification body (NQA) was impressed with our continued use and development of the system well ahead of the transition dead line of September 2018 and as such no non-conformities or observations were made during the audit.

 

For any additional information regarding our Quality Management system please Contact Us.

 

                                                                                                                  Michael Cummings

August 2017 - Fabri Company day

Fabri’s continuing professional development programme was extended this year to include Knockhill racing track, Scotland, where events included:

 

  • Rally Driving - complete the rally cross track without an insurance claim and the AA (all bar one!)
  • Formula Race Car Challenge – getting into (and out of!) a single seater race car!! – (and some track time too!)
  • Group Karting – yearly opportunity to expend ‘mad max’ fantasies……..no (serious) casualties!

 

A great day was had by all – and everyone drove home safely ……….

 

Dave Burnett

MAY 2017 - Burgan Oil Terminal - Cape Town

Burgan Oil Terminal construction phase is progressing well, with the anticipated completion by the end of Q2 2017.

Follow the link below to see progress to date;

 

Burgan Oil Terminal Progress

Douglas Burns

DECEMBER 2016 - Fabri Consulting Engineers - Christmas Dinner

This year Mister Singh's Glasgow hosted the Fabri Christmas Dinner. A great night enjoyed by all to close out a successful 2016. Enjoy the Christmas break as we look forward to the challenges 2017 will bring.

Michael Cummings

NOVEMBER 2016 - Quality Management Transition

Fabri have made the successful transition to ISO9001:2015 two years ahead of the deadline.

 

The Fabri quality management system was updated to reflect the new ISO9001: 2015 standard and the Construction Design and Management (CDM) 2015 regulations at the end of 2015.

 

Our transition / recertification audit was completed by an independent certification body NQA, who found no non-conformities or observations during the audit.

 

For any additional information regarding our Quality Management system please Contact Us.

 

                                                                                                                  Michael Cummings

JULY 2016 - Fabri Company Day

After last years MUD run a gentler approach was selected for the Fabri Company Day this year.......

 

In keeping with our business, it involved working with oil, working in hazardous areas, and selection of the appropriate PPE......

Dave Burnett

MARCH 2016 - Fabri Consulting Engineers - BP Amsterdam

With the sale of their Amsterdam Terminal, Fabri Consulting Engineers completes 8 years of delivering successful Projects at BP Netherlands Amsterdam Terminal.

 

Many long lasting friendships were made during our time at site, with the Scots, the Dutch, the Greek, the Germans - and even the English ;-) working well together. 

 

We wish the new owners well in their future development of the Terminal.

Dave Burnett

FEBRUARY 2016 - Fabri Consulting Engineers - New Website

New Year, New Website.... updated to reflect Fabri achievements over the last 10 years. 

 

Developed entirely  'in house' with contributions from all staff, we are confident you will find it informative - feel free to contact us if you have any comments.

Dave Burnett

Print Print | Sitemap
© Fabri Consulting Engineers