Fabri Consulting Engineers
Fabri Consulting Engineers

BP Oil UK

 

Following on from a long working relationship with BP Oil UK, Fabri Consulting have worked closely with BP Project Managers to deliver Projects at most of the UK mainland Terminals........

Hamble Fire Pumps

BP Hamble identified that fire water pump P121 was no longer working and needed to be replaced. As the terminal have reduced the number of storage tanks on the site with mainly only crude and ethanol remaining it was requested that Fabri investigated the option to reduce the size of the pump.

 

Fabri reviewed the site SSERP to identify what firefighting scenarios would be the most onerous on the pumping system and site capability. These scenarios where then hydraulicly modelled utilising the site jetty fire water pumps.

 

This hydraulic analysis determined that P121 (the electrically driven fire pump which served as the light oil tank farm fire pump) can be removed from the system completely as the diesel driven pumps at the jetty were found to supply sufficient flow and pressure for all remaining firefighting scenarios. 

 

Year

2023

 

Project Managers

Michael Cummings (Fabri) / Monique Wassili (BP)

 

Fabri Engineering Lead

David Burnett

Hamble Jetty Control Room

BP Hamble where looking at upgrading / replacing the messing facilities at the Jetty. The facility was believed to have fallen into a state of disrepair and as such Fabri where requested to explore the options for deconstructing the messing facility and incorporating/rationalising the equipment within the Jetty Control Room.

 

Fabri reviewed various options for replacing the existing building, deconstructing the existing building, locating a new smaller building in an alternative area of the jetty and rationalising the equipment within the jetty control room to allow the required space to house the messing facilities.

 

In addition to the above and in line with the BP Project Manager further inspection of the messing facility was recommended to enable repairs that would expand the life span of the building. Ultimately following detailed inspection it was identified that this was the most suitable option for BP to take forward.  

 

Year

2023

 

Project Managers

Tom Knight (Fabri) / Roy Smith (BP)

 

Fabri Engineering Lead

Lewis Doherty

IOG Fire and Explosion Hazard Management Plan (FEHMP) 

The scope of the project was to evaluate and determine the terminal’s Fire and Explosion Hazard Management Plan (FEHMP) for the various fire scenarios which may occur at BP Isle of Grain (IOG).

 

The FEHMP was based on a standard methodology from Energy Institute’s (EI) Model Code of Safe Practice Part 19 (EI 19) and was developed to provide a consistent approach to the implementation of fire protection and hazard mitigation systems for IOG. It was the intent to provide a uniform approach and guidance to utilise the firefighting systems in the most effective and efficient way possible in the event of a fire or explosion at the site.

 

This FEHMP utilises EI 19 to determine potential hazards at the site, prevention measures, mitigation measures, and response strategies.

 

Year

2022 / 2023

 

Project Managers

Michael Cummings (Fabri) / Roy Smith (BP)

 

Fabri Engineering Lead

Rori MacPherson

Interceptor Replacement Project

Fabri were asked to review the storm water process for the existing Rail Interceptor inclusive of all relevant standards.

 

Fabri confirmed the current interceptor was inadequate for the volume of contaminated water (oily water mix) in the rail drainage system with which it was intended for prior to discharge from site.

 

The proposal from this review highlighted a new retention interceptor would be required to allow surface water (oily water) to be discharged to a watercourse in-line with pollution prevention guidelines.

 

The project replaced the existing underground interceptor with a new larger volume tank which has the ability to capture all localised surface water.

Hydrocarbon detectors were also installed, where a localised MOV would close on detection.

 

The Project would take into account civil works comprising of a digging area of 8m (L) x 4m (W) x 7m (D). Given the size of the required digging area a confined space certificate was required inclusive of an emergency rescue which incorporated a confined space rescue.

 

Complete project from Appraise through to Construction and Commissioning

  • Compliance with BP CVP process
  • Mechanical, EC&I & Civil/Structural detailed design
  • Construction management and site supervision
  • Commissioning and handover

Year / Budget

2021 - 2022/ £300,000

 

Project Managers

Michael Cummings (Fabri) / Roy Smith (BP)

Slops Return Project

During piping integrity checks unexpected conditions were identified within the existing carbon steel slops piping system. The project replaced the 8” carbon steel slops discharge pipework with 4” stainless steel pipework.

  • Full EPCM
  • Compliance with BP CVP process
  • HAZOP
  • Mechanical, EC&I & Civil/Structural detailed design
  • Construction management and supervision
  • Commissioning and handover

Year / Budget

2020 - 2021/ £300K

 

Project Managers

Michael Cummings (Fabri) / Roy Smith (BP)

Second Import Line Project

Introduction of a second import line allowing site to simultaneously import and recirculate product from the main Jet storage tanks on site. Complete project from Appraise through to Construction.

  • Full EPCM
  • Compliance with BP CVP process
  • HAZOP
  • Mechanical, EC&I & Civil/Structural detailed design
  • Construction management and supervision
  • Commissioning and handover

Year / Budget

2020 / £370K

 

Project Managers

Dave Burnett (Fabri) / Roy Smith (BP)

Blending Upgrades FEED

Review options for a new blending facility inclusive of additional pumping requirements, micro filters, clay filters and filter water separators.

  • FEED study
  • Mechanical & Piping requirements
  • EC&I requirements
  • Civil & Structural requirements
  • Procurement
  • Liaison on with local planning authorities

Year

2019 - 2020

 

Project Managers

Dave Burnett (Fabri) / Roy Smith (BP) 

Engineering Support

Over a period of 10 years Fabri supported BP Oil UK engineering team develop and confirm compliance with there integrity management of all Fuel Value Chain (FVC) controlled terminals. This project covered many different elements and included the management and engineer support as required to complete the following;

  • HAZOP & LOPA studies
  • FEHMP implementation
  • ETP gap analysis
  • Pipeline integrity
  • Ethanol BRISK
  • Asset evaluation
  • Switch gear thermal graphic imaging

BP Northampton & Kingsbury - Tank Gauging Upgrade

Upgrade to existing tank gauging infrastructure to remove 'end of life' equipment

  • Feasibility study
  • Review available technology and compatibility with existing infrastructure
  • Full EPCM
  • Compliance with Client CVProcess
  • Detailed Design
  • Detailed Engineering PHSSER
  • Construction Management and Supervision
  • Commissioning and Handover

Year / Budget

2015 - 2016 / £500K

 

Project Managers

Thomas Knight (Fabri) / Iain Shearer (BP) 

More images from BP Oil UK Tank Gauging Project

BP Northampton & Kingsbury - Fire Protection

Project to introduce fire protection for both sites initially in preparation for the ethanol introduction however at the same time making allowance for site wide fire protection to align the sites with BP group practice standards GP 24-10 and GP 24-40.

 

The project included fire pump & foam proportioning unit control, electrically operated valve control, tank cooling, foam pourers, linear heat detection and flame detectors.

  • Compliance with BP CVP process
  • HAZOP & LOPA studies
  • Liaison with HSE and local fire authorities
  • Procurement management  
  • Mechanical and  EC&I detailed design
  • Commissioning

Project Managers

Douglas Burns (Fabri) / Peter Alderman (BP) 

More images from BP Oil UK Fire Protection Project

Other BP Oil UK Projects 2005 - 2020......

Projects complete at multiple sites across the UK;

  • Development of P&ID’s to GP 08-01
  • Ethanol FEED studies
  • Safety basis calculations
  • Fire protection
  • Tank venting reviews
  • Pipework identification
  • Tank gauging FEED studies
  • Water bottoms sparging
  • Product pump replacement
  • Through put reviews
  • COC replacement and introduction
  • Site planning expansion and new
  • Thermal relief reviews
  • Loading arm upgrades and replacement
  • Tannoy system upgrades
  • Surge analysis for new ROSOV’s
  • Dead stock reduction reviews
  • Control room upgrades
  • Pump upgrades

 

Year

2005 - 2023

 

 

 

 

Print | Sitemap
© Fabri Consulting Engineers